Table 9 – EVM Reporting Requirements

Table 9 is located in Enclosure 1 Section 5 Reporting Requirements.

 

Table 9. EVM Reporting Requirements
Contract Value Applicability Notes Source
< $20M Not required IPMR Should be used if cost and/or schedule reporting is requested by the PMO IPMR DID DI-MGMT-81861A*
≥ $20M & < $100M Required monthly when EVM requirement is on contract Formats 2, 3, and 4 may be excluded from the contract data requirements list (CDRL) at program manager discretion based on risk
≥ $100M Required monthly when EVM requirement is on contract All Formats must be included in the CDRL

Additional Information:
For ACAT I contracts, task orders, and delivery orders, IPMR data will be delivered to the EVM Central Repository.

The IPMR can be tailored to collect cost and/or schedule data for any contract regardless of whether EVM is required. For information on tailoring the IPMR, refer to the DoD IPMR Implementation Guide (Reference (cj)).

Formats and reporting requirements for the IPMR are determined and managed by USD(AT&L) through the office of PARCA.

Reporting thresholds are in then-year dollars.

DI-MGMT-81861A = Data Item Management-81861 (Reference (av))  